Superior Court of Pennsylvania.
J.W.S. DELAVAU, INC., Appellee,
v.
EASTERN AMERICA TRANSPORT & WAREHOUSING, INC., Appellant.
KELLY, J.
¶ 1 Appellant, Eastern America Transport and Warehousing, Inc.
("Eastern"), asks us to reverse the judgment entered in the
Philadelphia County Court of Common Pleas, awarding Appellee, J.W.S. Delavau
Company, Inc. ("Delavau"), monetary compensation for negligence,
breach of contract, conversion, and delay damages. In its cross_appeal from the
favorable judgment, Delavau asks us to determine whether the award of delay
damages in its favor should be recalculated to include the period between the
untimely death of the first trial judge and the second trial in the case. We
hold Delavau is entitled to the delay damages it requests for the period in
question. In all other respects, the judgment in favor of Delavau is affirmed.
Accordingly, we affirm in part, reverse in part, and remand with instructions.
¶ 2 The relevant facts and procedural history are as follows: Delavau is in
the business of manufacturing nutritional supplements. In the late 1980's,
Delavau began storing goods, predominantly calcium carbonate, at the Harbor
Warehouse (then known as the International Warehouse). On March 12, 1991, a fire
occurred at the Harbor Warehouse, and Delavau began looking for another storage
facility.
¶ 3 Eastern operated a public storage warehouse and approached Delavau to
express an interest in warehousing Delavau's goods. In September 1991, Delavau's
president met with Eastern's Chief Operation Officer ("COO") to
discuss Delavau's needs. Delavau informed Eastern that, inter alia, the
product was a nutritional supplement for human consumption and needed to be
stored in a clean, dry space.
¶ 4 Although Eastern's warehouse was over fifty years old, and a general
commodities warehouse as opposed to a food_grade warehouse, the space it offered
Delavau was clean and dry. Delavau was satisfied that it could properly and
safely store its product at Eastern's warehouse under the proffered conditions.
¶ 5 Eastern's COO and Delavau's president entered into negotiations and on
October 31, 1991, they both signed a letter outlining the understanding of the
deal. The letter set forth the price and other terms and conditions of the
agreement, including: (1) any product Delavau requested via faxed order
had to be released no later than the following morning; (2) Delavau's product
had to be kept in an exclusive, designated area; (3) Eastern had to provide
monthly activity reports; (4) Delavau was guaranteed access to its product at
all times; (5) any damage to Delavau's goods had to be reported to Delavau
immediately; (6) spray pesticides could not be used near Delavau's product; and
(7) storage prices were guaranteed for two years.
¶ 6 Delavau moved what it considered to be good product from Harbor to
Eastern. From 1991 through 1992, Delavau was consistently transporting product
to and from Eastern with each shipment being evidenced by a warehouse receipt
issued by Eastern and containing the pre_printed notation: "This receipt is
valid only when signed by an officer of the company." None of the receipts
issued to Delavau was signed in the ordinary sense, but each did contain the
computer_generated initials of the Eastern employee who prepared the warehouse
receipt. In many instances the receipt contained the initials "L.W.",
referring to Ms. Wilson, the warehouse administrator. Each receipt also
contained certain terms and conditions, including one clause which sought to
limit Eastern's liability for damages to 200 times the base storage rate, unless
the depositor paid a premium of 2/10 of one percent per month on the excess
valuation.
¶ 7 In June 1992, Delavau noticed that some of its product was returning
from Eastern's warehouse with wet marks. Delavau conducted an inspection of the
warehouse and found that Eastern's roof had suffered damage causing water
leakage. Delavau subsequently received assurances from Eastern that the problem
would be dealt with promptly. However, due to weather conditions and labor
issues, Eastern was unable to fix the roof for several months. During that time,
the roof's condition continued to deteriorate, causing a large amount of water
to fall and pool on and around Delavau's goods. Eastern did not inform Delavau
of the damage to its product. Instead, Eastern proceeded to house much of
Delavau's product out of the exclusive area to prevent further damage to the
product.
¶ 8 Delavau filed a claim with its insurance carrier, USF & G, for the
water damage to its product. When USF & G's agent attempted to photograph
the damaged product, Eastern turned him away. However, USF & G hired William
Comly of Eastern Services and Recovery Company, an independent recovery agency,
to complete an assessment and inventory of Delavau's product in Eastern's
warehouse. In that inventory, the goods were divided into four categories: good,
suspect, wet, and damaged.
¶ 9 After the inventory was complete, Eastern told Delavau to remove all of
its product from the warehouse. Delavau refused, saying that it only wanted to
remove the good product, and that it still intended to photograph the goods in
the warehouse. Delavau was never permitted to photograph its goods. Therefore,
in addition to refusing to remove its goods, Delavau stopped paying storage and
transportation fees to Eastern.
¶ 10 Delavau filed suit against Eastern alleging negligence, beach of
contract, and conversion. Eastern counterclaimed for transportation and unpaid
storage charges. The case was tried before the Honorable Berel Caesar in May and
June of 1997, and on June 30, 1997, Judge Caesar issued a verdict in favor of
Delavau and in favor of Eastern on its counterclaim. Judge Caesar vacated the
decision pending post_trial motions. October9, 1997, while the motions were
pending, Judge Caesar suddenly and accidentally died.
¶ 11 In February 2000, a new trial proceeded before the Honorable Joseph
Papalini. Following consideration of the parties' proposed findings of fact and
conclusions of law, on May 7, 2001, the trial court issued its verdict in favor
of Delavau in the amount of $1,368,000.00 and in favor of Eastern on its
counterclaim in the amount of $9,399.00, for a net award to Delavau of
$1,358,601.00. [FN1]
FN1. On May 21, 2000 Eastern's warehouse and its contents were completely
destroyed by fire.
¶ 12 Eastern filed post trial motions for judgment notwithstanding the
verdict ("JNOV"), a new trial, or a new trial as to damages only,
based upon assertions that Delavau had failed to sustain its burden of proof on
damages and the trial court had erroneously reduced Eastern's counterclaim.
Eastern also filed a motion to stay execution on the judgment. The court denied
Eastern's motions and awarded Delavau limited delay damages on its judgment. The
delay damages excluded the time period attributable to Judge Caesar's untimely
passing (October 9, 1997 to February 14, 2000). This timely appeal and
cross_appeal followed.
¶ 13 Eastern, in its appeal docketed at No. 3028 EDA 2001, raises the
following issues for our review:
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR WHEN IT FAILED TO ENFORCE A
PLAIN LIMITATION OF LIABILITY PROVISION CONSPICUOUSLY CONTAINED WITHIN
WAREHOUSE RECEIPTS WHICH DELAVAU RECEIVED, WITHOUT OBJECTION, UPON DELIVERY OF
EACH OF NUMEROUS SHIPMENTS OF GOODS TO EASTERN AMERICA'S WAREHOUSE OVER A 15
MONTH PERIOD?
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR WHEN IT CONCLUDED THAT DELAVAU
HAD NOT ABANDONED ITS GOODS AT THE EASTERN AMERICA WAREHOUSE, WHERE DELAVAU
EXERCISED NO RIGHTS OF POSSESSION OVER THE PROPERTY AND FAILED TO PAY
TRANSPORTATION AND STORAGE CHARGES WHICH IT OWED?
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR WHEN IT PERMITTED DELAVAU TO
DELEGATE ITS RESPONSIBILITY FOR STORAGE OF ITS GOODS UNDER "SANITARY
CONDITIONS," AS REQUIRED UNDER THE FEDERAL FOOD AND DRUG ADMINISTRATION
RULES AND REGULATIONS?
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR WHEN IT CONCLUDED THAT DELAVAU
HAD SUSTAINED ITS BURDEN OF PROOF ON DAMAGES, DESPITE THE FACT THAT DELAVAU
DID NOT TEST THE GOODS, DID NOT PRESENT EXPERT TESTIMONY, AND DID NOT PRESENT
ANY OTHER COMPETENT EVIDENCE TO INDIVIDUATE DAMAGES?
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR BY IMPROPERLY REDUCING EASTERN
AMERICA'S COUNTERCLAIM FOR STORAGE CHARGES WITHOUT LEGAL FOUNDATION?
(Eastern's Brief at 5).
¶ 14 Delavau, in its appeal docketed at No. 3124 EDA 2001, raises the
following issue for our review:
DID THE TRIAL COURT COMMIT REVERSIBLE ERROR WHEN IT REFUSED TO AWARD DELAY
DAMAGES FOR THE FORTY_MONTH PERIOD (OCTOBER 9, 1997 TO FEBRUARY 14, 2000)
BETWEEN THE DEATH OF THE FIRST TRIAL JUDGE, THE HONORABLE BEREL CAESAR, AND
THE REASSIGNMENT OF THE CASE TO THE HONORABLE JOSEPH I. PAPALINI, THE SECOND
TRIAL JUDGE, WHO ISSUED THE DECISION ON APPEAL, ON THE GROUND THAT SUCH DELAY
"WAS IN NO WAY THE FAULT OF EITHER SIDE"?
(Delavau's Brief at 3).
¶ 15 Review of a trial court's decision to deny post_trial motions in the
nature of a motion for JNOV and/or a new trial implicates the following standard
and scope of review:
A JNOV can be entered upon two bases: (1) where the movant is entitled to
judgment as a matter of law; and/or, (2) the evidence was such that no two
reasonable minds could disagree that the verdict should have been rendered for
the movant. When reviewing a trial court's denial of a motion for JNOV, we
must consider all of the evidence admitted to decide if there was sufficient
competent evidence to sustain the verdict.... Concerning any questions of law,
our scope of review is plenary. Concerning questions of credibility and weight
accorded the evidence at trial, we will not substitute our judgment for that
of the finder of fact.... A JNOV should be entered only in a clear case.
Our review of the trial court's denial of a new trial is limited to
determining whether the trial court acted capriciously, abused its discretion,
or committed an error of law that controlled the outcome of the case. In
making this determination, we must consider whether, viewing the evidence in
the light most favorable to the verdict winner, a new trial would produce a
different verdict. Consequently, if there is any support in the record for the
trial court's decision to deny a new trial, that decision must be affirmed.
Buckley v. Exodus Transit & Storage Corp., 744 A.2d 298, 304_5,
(Pa.Super.1999) (internal citations omitted).
¶ 16 Appellate review of a contracts case requires this Court to determine
whether the factual findings of the trial court are supported by competent
evidence on the record, and whether the trial court committed an abuse of
discretion. Stonehedge Square Ltd. Partnership v. Movie Merchants, Inc.,
454 Pa.Super. 468, 685 A.2d 1019, 1022 (1996), affirmed, 552 Pa. 412, 715
A.2d 1082 (1998). However, the trial court's conclusions of law are subject to
plenary review. Id. Keeping in mind these principles, we consider the
propriety of the trial court's decision to deny Eastern any post_ trial relief.
¶ 17 In its first issue on appeal, Eastern argues that the parties did not
intend to be bound solely by the terms of the October 31, 1991 letter. To the
contrary, Eastern insists that the contract was formed upon delivery of the
goods and issuance of the warehouse receipt. Eastern claims that its warehouse
receipts contain a conspicuous limitation of liability provision, which
constitutes a valid and binding term of the parties' "complete
contract."
¶ 18 Eastern further asserts that Ms. Wilson, as "warehouse
administrator", was the most appropriate person to sign the receipts, and
that she therefore must be considered an officer of Eastern. Eastern also
submits Ms. Wilson's computer_generated initials on the receipts comprise the
necessary "signature" by an officer of the company to validate the
warehouse receipts for purposes of rendering enforceable the limitation of
liability provisions contained therein. In support of its contention, Eastern
argues computer_generated initials must be deemed a "signature" in the
ordinary sense because initials satisfy the signature requirements under the UCC,
citing 13 Pa.C.S.A. ¤ 1201 (defining signature as "any symbol executed or
adopted by a party with present intention to authenticate a writing.").
Eastern also directs our attention to the testimony of Mr. Lieb, an employee of
Eastern, who stated that he believed Ms. Wilson was an officer of the company.
Thus, Eastern insists the trial court erred in determining that the
computer_generated initials were insufficient as a "signature" and
that Ms. Wilson was not "an officer of the company," thereby
precluding Eastern from invoking the liability limitation provisions contained
in its warehouse receipts. Eastern construes the storage contract between the
parties to include the terms outlined in October 31, 1991 letter and the
provisions contained on the warehouse receipts. To the extent the trial court
refused to enforce the provisions contained in the warehouse receipts as part of
the parties' agreement, Eastern concludes the court's decision should be
reversed. We cannot agree.
¶ 19 In response, Delavau argues that the parties intended to be bound
solely by the terms of the October 31, 1991 letter and not by the terms on the
warehouse receipts. Delavau claims that the bailment contract was formed when
the October 31, 1991 letter was signed, and not when its goods were delivered to
Eastern's warehouse.
¶ 20 Delavau further asserts that even if the bailment contract was formed
upon delivery of the goods, the terms on the warehouse receipt were not valid
and binding, because Eastern failed to satisfy its own condition precedent; i.e.
the receipts must be "signed by an officer of the
company." Delavau contends the record supports the trial court's finding
that Ms. Wilson was not an officer of Eastern. Delavau asserts that the phrase
"officer of the company" must be construed against Eastern as the
drafter of the receipts and therefore Eastern must prove that Ms. Wilson was an
"officer of Eastern," not merely that she was the most appropriate
person to sign the receipts.
¶ 21 Delavau also insists that computer_generated initials cannot be
considered "signatures" in the plain and ordinary sense of the word.
Delavau submits the trial court was correct in concluding that the UCC
definition was inapplicable, because, inter alia, the phrase "signed
by an officer of the company" was written by Eastern and is not a statutory
term. Delavau construes the storage contract between the parties to include the
terms outlined in October 31, 1991 letter but not the provisions
contained on the warehouse receipts. Delavau concludes we should affirm the
trial court. We agree.
¶ 22 The proper interpretation of a contract is a question of law to be
determined by the court in the first instance. Standard Venetian Blind Co. v.
American Empire Ins. Co., 503 Pa. 300, 305, 469 A.2d 563, 566 (1983). When
interpreting a contract, the goal is to determine the intent of the parties and
effect must be given to all provisions in the contract. Com., Dept. of Transp.
v. Manor Mines, Inc., 523 Pa. 112, 119, 565 A.2d 428, 432 (1989).
Importantly,
Under ordinary contract law, contracts are enforceable when parties reach
mutual agreement, exchange consideration and have set forth terms of their
bargain with sufficient clarity. Additionally, an agreement is definite if it
indicates that parties intended to make a contract and if there is an
appropriate basis upon which a court can fashion a remedy. Moreover, when the
language of the contract is clear and unequivocal, courts interpret the
meaning by its content.
Biddle v. Johnsonbaugh, 444 Pa.Super. 450, 664 A.2d 159, 163 (1995).
Also, once a contract has been formed, its terms may be modified only if both
parties agree to the modification and the modification is founded upon valid
consideration. Corson v. Corson's Inc., 290 Pa.Super. 528, 434 A.2d 1269
(1981).
¶ 23 We further note, a "contract is not ambiguous merely because the
parties do not agree on its construction." RESPA of Pennsylvania, Inc.
v. Skillman, 768 A.2d 335, 340 (Pa.Super.2001). Rather,
[c]ontractual language is ambiguous if it is reasonably susceptible of
different constructions and capable of being understood in more than one
sense. This is not a question to be resolved in vacuum. Rather, contractual
terms are ambiguous if they are subject to more than one reasonable
interpretation when applied to a particular set of facts. We will not,
however, distort the meaning of the language or resort to strained contrivance
in order to find an ambiguity.
Madison Const. Co. v. Harleysville Mut. Ins. Co., 557 Pa. 595, 606,
735 A.2d 100, 106 (1999) (internal citations and quotations omitted).
¶ 24 When a term is ambiguous, courts may construe the term against the
drafter of the document. Central Transp., Inc. v. Board of Assessment Appeals
of Cambria County, 490 Pa. 486, 417 A.2d 144 (1980); Molag, Inc. v.
Climax Molybdenum Co., 431 Pa.Super. 569, 637 A.2d 322 (1994). Further, when
applying a term as used in the UCC, it is most appropriate and indeed necessary
to use the definition given in the UCC itself. Triffin v. Dillabough, 448
Pa.Super. 72, 670 A.2d 684, 689 (1996), affirmed, 552 Pa. 550, 716 A.2d
605 (1998). However, where an unambiguous term is not being used in the context
of the UCC, it is most appropriate to apply the plain and ordinary meaning of
the term, regardless of whether the term is also defined in the UCC. Lebanon
Coach Co. v. Carolina Cas. Ins. Co., 450 Pa.Super. 1, 675 A.2d 279, 283
(1996), appeal denied, 546 Pa. 695, 687 A.2d 378 (1997) (holding when
interpreting contract, clear and unambiguous words must be given their plain and
ordinary meaning).
¶ 25 Instantly, the October 31, 1991 letter was the end_product of
substantial negotiations between the senior management of Eastern and Delavau
and was signed both by Eastern's COO and Delavau's President. The signed letter
set out the essential terms of the agreement and, until the current dispute
arose, the parties acted in conformity with that agreement. See Biddle,
supra. Thus, there is ample evidence in the record to support the trial
court's finding that the parties intended to be bound by the terms of the
October 31, 1991 letter, and that letter alone. Id. Therefore, the trial
court did not abuse its discretion in finding that the parties intended to be
bound by the October 31, 1991 letter.
¶ 26 Furthermore, Eastern is unable to point to anything in the record to
indicate Delavau either consented to the limitation of liability contained in
the warehouse receipt or that such a modification was supported by valid
consideration. Thus, the terms of the warehouse receipt were not part of the
contract betweenthe parties, and Delavau cannot be subject to any liability
provisions contained therein. See Corson, supra. It would demean the
importance of the written agreement if the parties could find themselves bound
by pre_printed terms and conditions on a warehouse receipt, especially after
they had engaged in extensive negotiations and mutually agreed to terms, which
did not include those contained in the warehouse receipt. [FN2] These facts
alone are sufficient to support the trial court's finding that Delavau was not
bound by the liability_limiting terms on the warehouse receipts.
FN2. Moreover, as the trial court noted, our sister courts which have
dealt with similar issues have concluded that a bailee is not entitled to
alter unilaterally a preexisting contractual agreement through a
subsequently issued warehouse receipt which contains terms different from
those contained in the original agreement. See De Cecchis v. Evers,
174 A.2d 463 (Del.Super.1961) (holding where contract previously formed, no
modification could be made without consent of both parties and consideration
and, therefore, liability provisions contained in subsequently issued
warehouse receipt not binding); Miller v. Newsweek, Inc., 660 F.Supp.
852 (D.Del.1987) (holding same); Abend v. Haberman, 281 A.D. 262, 119
N.Y.S.2d 488 (1953) (holding mailed receipt containing limitation of
liability subsequent to the formation of contract not binding); Grain
Dealers Nat. Fire Ins. Co. v. Union Co., 159 Ohio St. 124, 111 N.E.2d
256 (1953) (holding warehouse receipt containing limitation of liability
mailed 20 days after delivery of stored goods not binding).
¶ 27 Even if the parties had not intended the October 31, 1991 letter to be
the full and final understanding of the parties, Delavau was still not bound by
the liability_limiting provisions of the warehouse receipts, as Eastern did not
comply with the terms of those warehouse receipts. Here, the warehouse receipts
contained a provision which required an "officer of the company" to
"sign" the receipt. Nevertheless, the warehouse receipts contained
only the computer_generated initials of Eastern's warehouse administrator, not
the signature of a company official. Eastern's reliance on a single employee's
belief that Ms. Wilson (the warehouse administrator) was an "officer"
of Eastern is not sufficient for a finding of fact in favor of that belief.
Eastern did not produce evidence or testimony from someone intimately familiar
with its organizational structure to show Ms. Wilson was, in fact, an officer of
the corporation. Eastern chose to use the phrase "officer of the
company" and has the burden to show Ms. Wilson was indeed an officer of
Eastern. It is not enough to opine that she was the most appropriate person to
sign the receipts. See Central Transp., Inc., supra; Molag, supra.
Therefore, the trial court properly found Ms. Wilson was not an officer of the
company. Id. See also Lebanon Coach Co., supra.
¶ 28 Furthermore, as drafter of the receipts, Eastern had the opportunity to
make clear whether the warehouse administrator's computer_ generated initials
would be a sufficient signature to validate the warehouse receipts.
Computer_generated initials do not constitute a signature in the plain meaning
of the word. See Collegiate Dictionary copyright (c) 2001 by
Merriam_Webster, Inc. (stating, the word signature refers to "a: the
act of signing one's name b: the name of a person written with his or
her own hand.") (emphasis added). Ms. Wilson's computer generated
initials did not meet the plain meaning of the word "signature." See
Lebanon Coach Co., supra. Thus, the warehouse receipts issued by Eastern
were not "signed" in accordance with its own terms. Id.
¶ 29 In the alternative, Eastern suggests that "course of
performance" caused the terms on the receipts to be incorporated into the
parties' contract, even if the terms were not originally part of the agreement.
Specifically, Eastern claims Delavau received hundreds of warehouse receipts and
did not complain, which establishes a course of performance having the effect of
supplementing the contract with the additional terms on the receipt. In support
of its position, Eastern cites Kunststoffwerk Alfred Huber v. R.J. Dick,
Inc., 621 F.2d 560, 564 n. 6 (3d Cir.1980) (stating courts have generally
allowed course of performance to supplement and qualify terms of agreement)
(citing J. White & R. Summers, Uniform Commercial Code ¤ 3_3 (1972)), for
the proposition that "course of performance" may modify an agreement.
We disagree.
¶ 30 "Course of dealing" is a "sequence of previous conduct
between the parties which is fairly regarded as establishing a common basis of
understanding for interpreting their expressions and other conduct". 13
Pa.C.S.A. ¤ 1205(a). "Course of performance" is a sequence of conduct
between the parties subsequent to formation of the contract during performance
of the terms of the contract. See 1 White and Summers, Uniform Commercial
Code ¤ 3_3 (4th ed.). "Course of dealing" "may supplement or
qualify terms of an agreement", 13 Pa.C.S.A. 1205(c), whereas "course
of performance" may be used only to interpret a contract. See Matthews
v. Unisource Worldwide, Inc., 748 A.2d 219 (Pa.Super.2000), appeal
denied, 568 Pa. 664, 795 A.2d 977 (2000) (citing Atlantic Richfield Co.
v. Razumic, 480 Pa. 366, 390 A.2d 736 (1978)); 13 Pa.C.S.A. ¤ 2208(a).
[FN3]
FN3. Although "course of performance" is only mentioned in
Article 2 of the UCC governing the sale of goods, we note that "course
of performance" can also be relevant to determining the meaning of the
contract in dispute. See Atlantic Richfield Co. supra at 376 n. 6,
390 A.2d at 741 n. 6 (noting parties' "course of performance" is
always relevant to interpreting contract); 13 Pa.C.S.A. ¤ 1103.
¶ 31 Here, the warehouse receipts were issued subsequent to formation and
during performance of the contract. Therefore, any behavior with respect to the
receipts can only be considered "course of performance" and not
"course of dealing." Eastern does not provide any case law to suggest
Pennsylvania courts have allowed "course of performance" to alter or
supplement an agreement. To the contrary, Pennsylvania case law indicates
"course of performance" can only be used to interpret, but not to
supplement, the terms of an existing agreement. See Matthews, supra.
Accordingly, Delavau's behavior with respect to the receipts cannot cause the
liability_limiting term on the receipts to become part of the contract between
the parties. [FN4]
FN4. Even if "course of performance" could modify an agreement,
the "course of performance" in this case does not rise to the
level required to modify an agreement. Though not binding precedent, we
recognize the soundness of the reasoning in Willow Valley Manor v.
Trouvailles, Inc., 977 F.Supp. 700, 704 (E.D.Pa.1997) (stating,
"the mere repeated sending of a writing containing additional terms
does not, without more, give rise to modification of the existing
agreement").
¶ 32 Finally, Eastern argues if the liability_limiting term is part of the
contract, it is enforceable due to Delavau's willful breach of the contract. As
we have already concluded the liability_limiting provisions of the warehouse
receipts were not part of the parties' contract, we need not address this
assertion.
¶ 33 In its next issue, Eastern argues Delavau abandoned its goods by
failing to pay transportation and storage fees and by failing to remove its
product when asked to do so. Eastern asserts Delavau cannot recover for damage
to goods it has abandoned. Eastern concludes the trial court's decision on this
matter should be reversed. We disagree.
¶ 34 We note:
Abandonment involves an intention to abandon, together with an act or
omission to act by which such intention is apparently carried into effect. In
determining whether one has abandoned his property or rights, the intention is
the first and paramount object of inquiry, for there can be no abandonment
without the intention to abandon. Black's Law Dictionary, West
Publishing Co., Fifth Edition, p. 2 (1979). The intent to abandon is to be
determined from all of the facts and circumstances of the case. Russell v.
Stratton, 201 Pa. 277, 50 A. 975 (1902). The question of whether a
particular act amounts to an abandonment is generally one of intention. Eagan
v. Nagle, 378 Pa. 206, 106 A.2d 222 (1954). When deciding whether an
object has been abandoned, we must consider the nature of the property, the
acts and conduct of the parties in relation thereto and the other surrounding
circumstances. Gilberton Contracting Co. v. Hook, 255 F.Supp. 687
(E.D.Pa.1966).
Commonwealth v. Wetmore, 301 Pa.Super. 370, 447 A.2d 1012, 1014
(1982).
¶ 35 In this case, Delavau's valuable business product was housed in
Eastern's warehouse. At no time did Delavau ever directly communicate any
intention to abandon its goods. Its mere failure to pay certain fees does not
rise to an intent to abandon. Id. In fact, Delavau expressed a desire to
remove part of the goods from Eastern's warehouse but was prevented from doing
so by Eastern's insistence that Delavau remove the entire product from storage.
Further, Delavau was not allowed to photograph the product in the warehouse,
even though the parties' contract guaranteed Delavau access to its product at
all times. Delavau's behavior did not indicate intent to abandon. Id.
Thus, the trial court properly concluded Delavau did not intend to abandon its
property in Eastern's warehouse, and Eastern is not entitled to relief on this
basis.
¶ 36 Next, Eastern argues Delavau is legally obligated under FDA rules and
regulations to store its goods under "sanitary conditions" and that
such a responsibility cannot be delegated. Nevertheless, Eastern asserts the
trial court allowed Delavau to delegate its responsibility for the storage of
goods under "sanitary conditions" to Eastern. Eastern concludes it
should not be held liable for damage caused by Delavau's failure to store its
goods under "sanitary conditions" because Delavau was negligent per
se for choosing to store its goods with Eastern in the first place. We
disagree.
¶ 37 In the instant case, Eastern agreed to store Delavau's goods under dry,
sanitary conditions. Eastern failed to remedy the problems in the warehouse that
made the conditions wet and unsanitary. As Eastern had agreed to store Delavau's
goods in a dry, sanitary area, Eastern breached its contract with Delavau by
failing to do so. See Biddle, supra. The trial court appropriately found
Eastern had breached the contract by failing to provide the agreed_upon dry,
sanitary area for Delavau's goods. See Stonehedge Square Ltd. Partnership,
supra. Moreover, the evidence shows the warehouse was clean and dry when the
parties first entered into the agreement, and it was Eastern who failed to
remedy the deficiencies in its storage facilities. Thus, the record belies
Eastern's claim.
¶ 38 Next, Eastern argues that the record is not sufficient for Delavau to
meet its burden of proof with respect to damages, because Delavau did not
chemically test the product stored in Eastern's warehouse or provide expert
testimony to show damages. Eastern asserts the trial court erred in its finding
as a matter of fact that Easter denied Delavau the opportunity to test the
product. Eastern concludes Delavau failed to produce competent evidence on which
to base its claims for damages. We disagree.
¶ 39 We note:
Generally, under Pennsylvania law, damages need not be proved with
mathematical certainty, but only with reasonable certainty, and evidence of
damages may consist of probabilities and inferences. Although the law does not
command mathematical precision from the evidence in finding damages,
sufficient facts must be introduced so that the court can arrive at an
intelligent estimate without conjecture. Where the amount of damage can be
fairly estimated from the evidence, the recovery will be sustained even though
such amount cannot be determined with entire accuracy. It is only required
that the proof afford a reasonable basis from which the fact_finder can
calculate the plaintiff's loss.
Molag, Inc., supra at 324 (citation omitted). Where a party is
particularly familiar with its property, it is competent to approximate the
value of the property. Silver v. Television City, Inc., 207 Pa.Super.
150, 215 A.2d 335, 339 (1965).
¶ 40 Here, Delavau is a major supplement manufacturer and has been involved
in the manufacture and sale of calcium product for many years. Delavau is
competent to approximate the value of the damaged product at Eastern's
warehouse. See id. At trial, Delavau's Vice_President of Finance and
Administration testified regarding financial calculations quantifying the value
of Delavau's pallets of product stored in Eastern's warehouse. See Molag,
Inc., supra. Also, the trial court appropriately found Eastern effectively
prevented Delavau from obtaining samples of its product for the chemical testing
that it now claims Delavau should have undertaken to prove its damages.
Therefore, we conclude Delavau met its burden of providing competent evidence on
which to base its claims for damages. Id.
¶ 41 In its fifth issue, Eastern asserts that it stored Delavau's product
until the May 2000 fire and it is entitled to storage and transportation fees
through May 2000, and not just until July 1, 1993. Eastern concludes the trial
court erred in reducing Eastern's counterclaim for storage and transportation
fees. We disagree.
¶ 42 A party that materially breaches a contract cannot be awarded
compensation for damages resulting from the other party's subsequent refusal to
perform its obligations under the contract. Ott v. Buehler Lumber Co.,
373 Pa.Super. 515, 541 A.2d 1143, 1145 (1998) (stating "The general rule is
that a party who has materially breached a contract may not complain if the
other party refuses to perform his obligations under the contract." A party
also may not insist upon performance of the contract when he himself is guilty
of a material breach of the contract) (citations omitted).
¶ 43 Here, the October 31, 1991 letter/contract specifically stated:
"We [Delavau] will have access to our [Delavau's] product at all
times." By refusing to allow Delavau to photograph its product, Eastern
prevented Delavau from exercising its contractual right to full access to its
product. Thus, Eastern breached a term of its agreement with Delavau. See id.
Furthermore by preventing Delavau from photographing its product, Eastern
essentially prevented Delavau from removing its product, because removal before
photographing would have permanently deprived Delavau of the opportunity to
document the damage to its product while still in Eastern's warehouse. Moreover,
Eastern had already breached the contract when it failed to maintain as clean
and dry the area of its warehouse designated exclusively for Delavau's product;
when it unilaterally moved Delavau's product from the designated area in
abrogation of the express terms of the agreement, and did not notify Delavau of
the removal; and when it failed to notify Delavau of the damage the leaking roof
had caused to its product. Due to Eastern's own material breaches of the
parties' agreement, the trial court correctly determined Eastern was not
entitled to damages subsequent to June 1, 1993. Id.
¶ 44 In its cross appeal, Delavau argues Eastern did not make a qualifying
offer of settlement pursuant to Pa.R.C.P. 238(a)(1). Further, Delavau submits it
did not cause the delay of the second trial. Delavau concludes it is entitled to
an award for delay damages, including the period between October 9, 1997 and
February 14, 2000, which is the time between Judge Caesar's untimely death and
the second trial in this case. We agree.
¶ 45 The text of the Rule 238 states:
At the request of the plaintiff in an action seeking monetary relief for
bodily injury, death or property damage, damages for delay shall be
added to the amount of compensatory damages awarded against each defendant
found to be liable to the plaintiff in the verdict of a jury, in the decision
of the court in a nonjury trial ... and shall become part of the
verdict, decision or award.
Pa.R.C.P. 238(a)(1) (emphasis added). Rule 238 mandates the imposition of
delay damages for the period of time, as provided in the Rule, during which
there has been no qualified offer of settlement proposed by the defendant, and
the plaintiff did not cause the delay. Id. Moreover, the Rule provides no
exception that applies when the delay cannot be attributed to either party. King
v. Southeastern Pennsylvania Transp. Authority, 383 Pa.Super. 420, 557 A.2d
11 (1989) (en banc ); Miller v. Wise Business Forms, Inc., 381
Pa.Super. 236, 553 A.2d 443 (1989) (en banc ). The defendant/appellee in Miller
failed to make an adequate settlement offer prior to trial, and after receiving
a verdict the plaintiff/appellant sought Rule 238 delay damages. The trial court
acknowledged the agreement of the parties that neither party was responsible for
the delay. Reasoning defendant/appellee should not bear the burden of paying for
a delay he did not cause, the trial court denied delay damages. On appeal, this
Court reversed the trial court's decision, holding the defendant/appellee was
responsible for Rule 238 damages even though he did not cause the delay. Id.
at 446_47.
¶ 46 In King, this Court had the opportunity to elaborate on the Miller
decision. As in Miller, the defendant/appellant in King failed to
make an adequate settlement offer prior to trial. After receiving a jury
verdict, the plaintiff/appellee moved for Rule 238 delay damages. The trial
court determined the cause of delay was the backlog in the court system, and not
attributable to either party. Nevertheless, the trial court held Rule 238
requires the defendant/appellant to pay delay damages even though that party was
not at fault. This Court affirmed, holding: "Where the defendant has not
made an adequate settlement offer pursuant to Rule 238(b)(1) and the plaintiff
has not caused the delay of the trial as noted in Rule 238(b)(2), there is no
basis on which to deny the plaintiff an award of delay damages." See
King, supra at 13 (internalquotations omitted). Likewise, we concluded
"[t]he drafters of the new rule have not allowed for the exclusion
of periods of delay not caused by either party." See id. (internal
quotations omitted) (emphasis in original).
¶ 47 Here, it is undisputed that Eastern did not make a qualifying offer of
settlement and that the delay, due to the sudden death of Judge Caesar, was not
the fault of either party. Id. Nevertheless, the fact that the delay was
not caused by Eastern does not relieve Eastern of liability for delay damages. See
id.; Miller, supra. The language in Rule 238 is mandatory. It does not
extend discretion to the trial court to exclude a period of time from the
calculation of delay damages where the defendant was not at fault. See
Pa.R.C.P. 238. Therefore the trial court erred when it excluded the time between
October 9, 1997 and February 13, 2000 from the calculation of delay damages
awarded to Delavau. Id. Consequently, we reverse and remand the matter to
the trial court to recalculate delay damages in favor of Delavau to include the
period of October 9, 1997 and February 13, 2000.
¶ 48 For the foregoing reasons, we hold Delavau is entitled to delay damages
for the time between the untimely death of the first trial judge and the second
trial in the case. Accordingly, we affirm the judgment in favor of Delavau in
all other respects, but reverse and remand for the recalculation of delay
damages consistent with this opinion.
¶ 49 Judgment affirmed in part, reversed in part; case remanded with
instructions. Jurisdiction is relinquished.